Rehabilitation
Rehabilitation of the Al-Sharash water complexes
A two-part project in Al-Sharash, Basra Governorate: maintenance and rehabilitation of six water treatment complexes, and construction of networks and extension of water lines in high-density polyethylene (HDPE) pipe across seven areas.
- 6 complexesWater complexes rehabilitated
- 7 networksWater networks across Al-Sharash
- 81 kmTotal length of HDPE pipe
- 110–225 mmNetwork pipe diameters
Part one
Maintenance and rehabilitation of the complexes
The complexes: Al-Jal’a, Al-Kareem, Al-Suwailih, Al-Hamdawi, Shalhat Al-Mouhi and Al-Shaheen.
- Rehabilitation of sedimentation, collection and mixing tanks: cleaning, sandblasting and food-grade epoxy coating.
- Replacement of inclined settling plates, filter media, filter nozzles and valves.
- Supply and installation of alum and chlorine systems.
- Associated mechanical and civil works: piping, intake structures, control rooms and operators’ rooms.
Works at each complex
Al-Jal’a
- Sedimentation tanks
- Cleaning, sandblasting and rust removal; replacement of damaged inclined settling plates (lamella) with polyethylene or GRP plates; cutting and welding; internal food-grade epoxy coating and external anti-rust coating; 8-inch butterfly valves.
- Collection and mixing tanks
- Sandblasting, repair of damaged steel, internal and external coating, 4-inch butterfly valves.
- Filters
- Replacement of sand and gravel layers; maintenance and internal and external coating; replacement of corroded steel; support of the nozzle plate and replacement of nozzles; 8-, 4- and 3-inch valves.
- Chlorine and alum
- Wall-mounted chlorinators with 10 bar booster pumps, copper and PPR piping, an alum mixer and dosing pump.
- Civil and service works
- Repair of the concrete base, roof waterproofing, refurbishment of the sanitary facilities, LED lighting, a new perimeter fence and a sliding main gate.
Al-Kareem
- Filters and tanks
- Full sandblast cleaning; replacement of damaged settling plates; welding and replacement of corroded parts; food-grade epoxy and external protection; replacement of 8-, 6-, 4- and 3-inch valves.
- Alum and chlorine
- Alum units, pumps and dosing pumps of 140 L/h, and chlorinators with booster pumps and accessories.
- Control room
- Removal of the old cabin and construction of a new main control room with sanitary facilities: earthworks and concrete, masonry and finishes, plumbing, electrical and air-conditioning installations.
Al-Suwailih
- Intake pipe
- Replacement of the intake pipe with 400 mm ductile iron pipe along the intake structure to the sedimentation tanks, including laying, jointing, testing and support with metal clamps.
Al-Hamdawi
- Clarifiers and filters
- Maintenance of the vertical clarifiers; filter cleaning; a new nozzle floor with horizontal and vertical supports; a maintenance hatch; internal food-grade epoxy and external coating; supply of nozzles and gravel and sand layers.
- Mechanical works
- Reuse of the old clear-water pipe as a header; 400, 200 and 160 mm carbon steel piping for backwash, overflow and air; supply and installation of air blowers.
- Valves and systems
- Gear-operated butterfly valves in various diameters; maintenance of the collection tanks; an alum system (mixer and 220 L/h dosing pump); a 4 kg/h chlorine system with a 16 bar booster pump.
Shalhat Al-Mouhi
- Tanks and filters
- Sedimentation tanks: cleaning and sandblasting, replacement of settling plates, welding and coating, 8-inch valves. Maintenance of the collection tanks. Filters: replacement of filter media, nozzles and 10-, 8-, 6- and 4-inch valves.
Al-Shaheen
- Internal facilities
- Maintenance of the sedimentation and collection tanks and filters: cleaning and silt removal, sandblasting, replacement of settling plates, filter media, nozzles and valves.
- Intake structure and station
- Replacement of the header of the delivery pumps and low-lift pumps with 8- and 10-inch carbon steel piping; construction of the intake structure, a walkway, a canopy and a station on driven steel sections; construction of an operators’ room and sanitary facilities.
Part two
Water networks and lines
The works on each network follow the sequence below, in addition to submitting geographic information system (GIS) drawings, coordinating with the relevant departments where services conflict, and supplying and installing house connections.
- Trench excavation
- DewateringWhere groundwater is present
- Sand bedding and pipe laying
- Hydrostatic testing
- Backfilling with fine soilWith compaction
- ReinstatementConcrete and asphalt surfaces
Pipe lengths in the seven networks
| Network | 225 mm | 160 mm | 110 mm | Connections and notes |
|---|---|---|---|---|
| Al-Ghumaij — forest side | 1,000 | — | 2,500 | 10 atm pressure pipe; connections and a 200 mm gate valve |
| Khalaf Al-Bazl | 5,000 | — | 4,500 | One 200 mm connection |
| Mayyah Al-Kour | 3,000 | — | 13,000 | Connections to previously laid pipes |
| Muzairi’a | — | 4,000 | 15,000 | Connection to the earlier networks |
| Bani Skain and Bait Darjal (north of Muzairi’a) | — | — | 5,000 | Additional connections |
| Al-Multaqa district | — | 5,000 | 15,000 | Connection fittings and house connections |
| Al-Na’eem and Al-Subaih line | — | 3,000 | 5,000 | 7 main tie-in points to the existing networks |
| Total | 9,000 | 12,000 | 60,000 | 81,000 linear meters |
HDPE pipe lengths in linear meters for each diameter.
Construction stages in pictures
From trench excavation to backfilling
More photographs from the network works
Other projects and references
See other work
Execution contractWastewater and stormwater stations — Izz al-Din Salim
Mechanical and electrical works for the wastewater and stormwater stations; 75-day duration.
View project
SubcontractorShalamcheh–Basra railway bridge over the Shatt al-Arab
Subcontractor on the railway bridge over the Shatt al-Arab, part of the Iraq–Iran rail link.
View project
Technical reference — BasraAl-Abbas drinking water treatment plant
Conventional surface-water treatment plant in Basra with a total capacity of 130,000 m³/day.
View projectRequest a study or proposal
Start with your project data.
Send us your project data. Our technical team reviews it and comes back with the right next step: a preliminary study, or a technical and commercial proposal.
Data that helps us prepare the proposal
- The water source and a recent analysis of it.
- The required capacity and its unit: m³/day or m³/h.
- The required product-water or effluent quality.
- The project site, available area and power source.
- The scope required: study, supply, or full execution.
- The expected project schedule.