Subcontractor

Shalamcheh–Basra railway bridge over the Shatt al-Arab

A railway bridge over the Shatt al-Arab river, part of the Iraq–Iran rail link project. Handasat Al-Mualaja works on the project as a subcontractor.

  • 7 boreholes50 to 62.1 m deep
  • 150 & 180 cmBored pile diameters
  • 45 & 50 mApproximate pile lengths
  • Balanced cantileverSuperstructure construction method

Overview

Project name
Railway bridge project (Shalamcheh–Basra) over the Shatt al-Arab river
Company role
Subcontractor
Superstructure
Precast, prestressed concrete segments erected by the balanced cantilever method
Foundations
Bored cast-in-place concrete piles reaching the bearing stratum, topped by concrete pile caps
Investigations
7 exploratory boreholes with in-situ and laboratory soil tests

The technical data on this page describes the project as a whole.

Piling equipment in the Shatt al-Arab channel beside the existing bridge.
Piling equipment in the Shatt al-Arab channel beside the existing bridge.

Soil investigation

Soil layers and the depth of the bearing stratum

The geotechnical investigation established the sequence of soil layers and the depth of the bearing stratum on which the bridge piles rest.

0102030405060 Depth (m) Type 1 150 cm dia. · about 45 m Type 2 180 cm dia. · about 50 m Steel casing, first 24 m Groundwater 2.4–5.3 m Low- to high-plasticity clay with sandy silt layers Transition zone 40–45 m Very dense silty sand SPT > 50
Simplified illustrative section of the soil and piles. The positions of the sandy silt layers are symbolic and the depths are approximate.

Exploratory boreholes

Number
7 boreholes: BH-1 to BH-7
Drilling method
Rotary drilling
Diameters
93 mm and 112 mm
Depths
50 m to 62.1 m

Groundwater

Groundwater level in the land boreholes ranges between 2.4 m and 5.3 m.

Sequence of soil layers

  • Upper and middle layers: low- to high-plasticity clay interbedded with layers of sandy silt.
  • Lower layers: from a depth of about 40 to 45 m the soil changes to very dense silty sand, the main bearing stratum for the piles, where standard penetration test values exceed 50 blows.

In-situ and laboratory tests

  • Standard penetration test (SPT).
  • Direct shear test (DST).
  • Unconfined compression test (UCT).
  • Triaxial test (UU).
  • Consolidation test (CT).

Structural specifications

Superstructure, foundations and materials

Superstructure

  • Precast, prestressed concrete segments produced by match casting (match-cast segmental PSC).
  • Erection by the balanced cantilever method.
  • Concrete with compressive strengths of 400, 450 and 500 kg/cm².
  • Ordinary Portland cement (Type I).

Foundations and piles

  • Bored, cast-in-place concrete piles.
  • The piles pass through the soil layers to the bearing stratum, where the standard penetration test value exceeds 50 blows.
  • The piers are built in two main types, each with a concrete pile cap.

Cement and waterproofing

  • Sulfate-resisting cement (Type II) at a content of not less than 360 kg/m³ with microsilica for all parts in contact with soil or water.
  • Waterproofing with bitumen or bituminous membrane.

Reinforcement and prestressing

  • Reinforcing steel with a yield stress of 4000 kg/cm².
  • Low-relaxation prestressing strands (ASTM A416 Grade 270), 15.24 mm in diameter.
  • 110 mm HDPE ducts for the tendons, and a Freyssinet anchorage system.

The two pier foundation types

ItemType 1Type 2
Number of piles9 piles12 piles
Pile diameter150 cm180 cm
Pile lengthabout 45 mabout 50 m
Steel casing—not less than 15 mm thick over the first 24 m
Pile cap dimensions9.0 × 9.0 × 2.0 m11.3 × 15.0 × 2.0 m

Concrete classes

ElementClass
Piles300 kg/cm²; 18–20 cm slump with superplasticizers
Pile caps350 kg/cm²
Columns400 kg/cm²
Superstructure400, 450 and 500 kg/cm²

Request a study or proposal

Start with your project data.

Send us your project data. Our technical team reviews it and comes back with the right next step: a preliminary study, or a technical and commercial proposal.

Data that helps us prepare the proposal

  • The water source and a recent analysis of it.
  • The required capacity and its unit: m³/day or m³/h.
  • The required product-water or effluent quality.
  • The project site, available area and power source.
  • The scope required: study, supply, or full execution.
  • The expected project schedule.